Leak repair requirements: Type III practice

10 published questions in this topic. Free Leak repair requirements practice for EPA 608 Type III, with instant feedback, explanations and source links.

10 published questionsFeedback appears after each answer
Type III · Leak repair requirementsQuestion 1 of 10

When a low-pressure appliance exceeds its trigger rate, the owner must repair the leaks within:

Answer choices for question 1

Keyboard: A–D to choose · Enter to check

Type III · Leak repair requirementsQuestion 2 of 10

A low-pressure centrifugal chiller cooling an office building with 1,000 lb of R-123 falls under which leak-rate trigger?

Answer choices for question 2

Keyboard: A–D to choose · Enter to check

Type III · Leak repair requirementsQuestion 3 of 10

A comfort cooling chiller that exceeded its trigger rate must have leak inspections:

Answer choices for question 3

Keyboard: A–D to choose · Enter to check

Type III · Leak repair requirementsQuestion 4 of 10

A retrofit or retirement plan for a leaking appliance must be kept:

Answer choices for question 4

Keyboard: A–D to choose · Enter to check

Type III · Leak repair requirementsQuestion 5 of 10

After an owner creates a retrofit or retirement plan for a leaking appliance, EPA can relieve the owner of the obligation to retrofit or retire if:

Answer choices for question 5

Keyboard: A–D to choose · Enter to check

Type III · Leak repair requirementsQuestion 6 of 10

Owners of appliances that exceed the leak rate must perform which tests at the end of repair?

Answer choices for question 6

Keyboard: A–D to choose · Enter to check

Type III · Leak repair requirementsQuestion 7 of 10

Purged refrigerant destroyed at a verified destruction efficiency of at least ___ may be excluded from leak-rate calculations.

Answer choices for question 7

Keyboard: A–D to choose · Enter to check

Type III · Leak repair requirementsQuestion 8 of 10

Appliances with 50 lb or more that leak 125% or more of their full charge in a calendar year must be reported to EPA by:

Answer choices for question 8

Keyboard: A–D to choose · Enter to check

Type III · Leak repair requirementsQuestion 9 of 10

Section 608 leak repair requirements (40 CFR 82.157) for an R-123 low-pressure chiller apply when the full charge is:

Answer choices for question 9

Keyboard: A–D to choose · Enter to check

Type III · Leak repair requirementsQuestion 10 of 10

A low-pressure chiller used to cool an industrial process (e.g., a chemical plant) with 50+ lb falls under which trigger rate?

Answer choices for question 10

Keyboard: A–D to choose · Enter to check

Ready for a full-length run?

Take a free timed mock for Type III or the full Universal: real section length and pass mark, instant score, no signup.

About this topic

Leak repair requirements and timelines. This page draws 10 questions from the 10 sourced Type III questions we have on leak repair requirements; each answer explains why and links to the rule it tests.

On the real test: Every Type III section on the real exam has 25 questions drawn across all Type III topics, and you need 18 of 25 (70%) on the closed-book test. Our bank has 10 practice questions on this topic. Expect questions like: “A low-pressure centrifugal chiller cooling an office building with 1,000 lb of R-123 falls under which leak-rate trigger?” and “A low-pressure chiller used to cool an industrial process (e.g., a chemical plant) with 50+ lb falls under which trigger rate?”

Key facts to remember

  • Chronic leaker report 125% of full charge in a year, report by March 1 (source)
  • Leak rate trigger: comfort cooling 10% (source)
  • A low-pressure centrifugal chiller cooling an office building with 1,000 lb of R-123 falls under which leak-ra 10% comfort cooling (source)
  • A low-pressure chiller used to cool an industrial process (e.g., a chemical plant) with 50+ lb falls under whi 30% (source)